← All off-plan projects

Dubai Land Residence Complex (Wadi Al Safa 5)

Developer: TIME PROPERTIES

Source: Dubai Land Department project register (Dubai Pulse).

DLD project number
2541
Status
ACTIVE
Completion (inspection)
59.3%
Target end date
2026-06-01
Completion date
2026-06-01
Start date
2023-01-01
Area
Wadi Al Safa 5
Master community
Dubai Land Residence Complex
Project type
—
Classification
—
Total units
304
Buildings / villas
1 buildings · 0 villas
Escrow agent
—
Master developer
DUBAI LAND RESIDENCES (L.L.C)

Description

1 Basement+Ground+3 Podiums+16 Typical/Residential Floors.The project designed to have a concrete structure and block with internal and external finishes.